This post is to notify you of new lane closures for the SH146 project:
SH146 will have alternating lane closures near Marvin Circle from 9:00am to 3:00pm on 1/7/20. This closure is to sawcut pavement in preparation of installing storm sewer. Two-way traffic will be maintained.
SH146 will have alternating lane closures near Marvin Circle from 9:00pm to 5:00am from 1/13/20 to 1/17/20. This closure is to install storm sewer under the highway. Two-way traffic will be maintained.
SH146 will have alternating lane closures from FM2094 to SH96 from 6:00am to 12:00am on 1/11/20. This closure is to install concrete barriers and restripe the road. Two-way traffic will be maintained.
The outside (right) northbound lane on SH146 will be closed on the Clear Creek Bridge (Seabrook/Kemah Bridge)from 9:00pm to 5:00am on the night of 1/8/20. This closure is to set concrete girders on the NB Arterial Widening.
Main Street in Seabrook will have alternating closures at SH146 from 9:00am to 3:00pm from 1/8/20 to 1/10/20. This closure is to install a new water line. Two-way traffic will be maintained. Flaggers and police officers will be used as-needed.
Miramar Green in Seabrook will have alternating closures at SH146 from 9:00am to 3:00pm from 1/7/20 to 1/9/20. This closure is to install a new storm sewer. Two-way traffic will be maintained. Flaggers and police officers will be used as-needed.
Marvin Circle in Seabrook will have alternating closures at SH146 from 9:00am to 3:00pm from 1/7/20 to 1/10/20. This closure is to install a new storm sewer. Two-way traffic will be maintained. Flaggers and police officers will be used as-needed.
E Meyer Avenue in Seabrook will have alternating closures at SH146 from 9:00am to 3:00pm from 1/7/20 to 1/10/20. This closure is to install a new storm sewer. Two-way traffic will be maintained. Flaggers and police officers will be used as-needed.
Kenneth Royal Drive in Seabrook will have alternating closures at SH146 from 7:00am to 5:00pm from 1/11/20. This closure is to install a new storm sewer. Two-way traffic will be maintained. Flaggers and police officers will be used as-needed.
The outside (right) southbound lane on SH146 will be closed on the Clear Creek Bridge (Seabrook/Kemah Bridge)from 9:00pm to 5:00am on the nights of 1/15/20 and 1/16/20. This closure is to set concrete girders on the SB Arterial Widening.
The outside (right) northbound lane on SH146 will be closed for at least 36 consecutive hours on the existing Clear Creek Bridge (Seabrook/Kemah Bridge) from 11:00pm 1/16/20 through approximately 3:00pm 1/18/20. The first 12 hours of this closure will allow for pouring a new section of bridge deck for the northbound widening. The following 24 hours of this closure are to minimize vibrations that could cause cracking in the newly poured deck.
The inside (left) lane will remain open so no detour is needed. Expect delays during the morning rush hour periods.
These closures are subject to change if needed due to weather. Uniformed Police Officers will be onsite to assist if needed.