This post is from TxDOT to notify you on new lane closures for the SH146 project:
N Meyer Avenue in Seabrook will have alternating lane closures at SH146 from 9:00am to 3:00pm on 12/5/19. This closure is to install concrete storm sewer. Flaggers and police officers will be used as-needed to maintain two-way traffic.
The intersection of FM2094 and SH146 will have alternating lane closures from 9:00am to 3:00pm on 12/5/19. This closure is to install new traffic signal cables. Flaggers and police officers will be used as-needed.
3rd Street in Seabrook will be fully closed at SH146 from 5:00am 12/11/19 to 7:00am 12/12/19. This closure is for new concrete paving. Detours are as follows: Detour: Use 3rd Street to N Meyer Ave to detour around the closure.
4th Street in Seabrook will be fully closed at SH146 from 5:00am 12/12/19 to 7:00am 12/13/19. This closure is for new concrete paving. Detours are as follows:Detour: Use Main Street to Cook Avenue to detour around the closure.
The outside (right) northbound lane on SH146 will be closed on the Clear Creek Bridge (Seabrook/Kemah Bridge) nightly on 12/18/19 and 12/19/19 from 9:00pm to 5:00am. This closure is for setting concrete girders on the northbound widening.
These closures are subject to change if needed due to weather. Uniformed Police Officers will be onsite to assist if needed.