TxDOT Update September 1

This post is to notify you of new lane closures for the SH146 project:

  1. The outside (right) eastbound lane on FM2094 will be closed at SH146 9:00am to 3:00pm on 9/2/20.  This closure is for construction of a bridge foundation.  No off duty police officers are anticipated to be used in this closure.

  2. The inside (left) eastbound lane and the inside (left) westbound lane on FM2094 will be closed at SH146 9:00am to 3:00pm on 9/3/20.  This closure is for utility locating.  No off duty police officers are anticipated to be used in this closure.

FULL CLOSURES:

  1. FM2094 will be fully closed just west of SH146 9:00pm Sunday through 5:00am Friday each week between 9/14/20 and 10/16/20.  The road will be open between 5:00am Friday and 9:00pm Sunday each week.  This closure is for construction of bridge foundations.  6 off duty police officers are anticipated to be used in this closure.

    1. Detour for traffic on SH146: FM2094 can be accessed by turning west of FM518 until you reach FM2094.

    2. Detour for traffic on FM2094: SH146 can be reached by traveling west on FM2094, south on FM270, and east on SH96.

  1. The eastbound lanes of FM518 will be fully closed just west of SH1469:00pm Sunday through 5:00am Friday each week for approximately one month, beginning immediately after the closure at FM2094.  The road will be open between 5:00am Friday and 9:00pm Sunday each week.  The westbound lanes will remain open.  This closure is for construction of bridge foundations.  6 off duty police officers are anticipated to be used in this closure.

    1. No detour needed for traffic on SH146 because westbound FM518 will remain open.

    2. Detour for traffic on FM518: turn south on Kemah Avenue, then east on Bel Road.

 These closures are subject to change if needed due to weather. 

Aerial photo showing the closure area at FM2094

Aerial photo showing the closure area at FM2094

Aerial photo showing the closure area at FM518

Aerial photo showing the closure area at FM518