This post is to notify you of new lane closures for the SH146 project:
There will be alternating lane closures at the intersection of SH146 and Repsdorph Road from 9:00am to 3:00pm on 7/6/20 to 7/10/20. This closure is for installation of new temporary traffic signals. Two-way traffic will be maintained.
There will be alternating lane closures on Shipyard Dr./10th St. from 9:00am to 3:00pm on 6/30/20. This closure is for the overhead demolition of bridge rail on the existing bridge.
The outside (right) southbound lane on SH146 will be closed from Capri Lane to 1st Street in Seabrook from 9:00am to 3:00pm on 6/30/20 and 7/2/20. This closure is for delivery of construction materials.
These closures are subject to change if needed due to weather.