This post is to notify you of new lane closures for the SH146 project: 

  1. First Street in Seabrook will be fully closed at SH146 9:00am to 3:00pm daily from 12/16/20 to 12/18/20. This closure is for construction of storm sewer. No off duty police officers are anticipated to be used in this closure. 

  2. There will be alternating lane closures in both directions of E Meyer Avenue at SH146 in Seabrook 9:00am to 3:00pm daily from 12/14/20 to 12/18/20. This closure is for construction of storm sewer. No off duty police officers are anticipated to be used in this closure. 

  3. The outside (right) westbound lane on NASA Road 1 will be closed just west of SH146 7:00am to 4:00pm on 12/12/20. This closure is for construction of storm sewer. No off duty police officers are anticipated to be used in this closure. 

  4. The outside (right) southbound lane on SH146 will be closed between Humble Drive and Repsdorph Road 9:00am to 3:00pm daily from 12/14/20 to 12/18/20. This closure will also take place from 7:00am to 4:00pm on 12/12/20. This closure is for retaining wall construction. No off duty police officers are anticipated to be used in this closure. 

  5. The outside (right) southbound lane on SH146 will be closed between Capri Lane and Shipyard Drive 6:00am to 6:00pm on 12/12/20. This closure is for preparation to set concrete girders. No off duty police officers are anticipated to be used in this closure. 

*REMINDER* Full Closures: 

  1. FM2094 will be fully closed just west of SH146 5:00am Monday 12/14/20 through 5:00am Friday 12/18/20. This closure is for construction of storm sewer. 4 off duty police officers are anticipated to be used in this closure.

    1. Detour for traffic on SH146: FM2094 can be accessed by turning west on FM518 until you reach FM2094.

    2. Detour for traffic on FM2094: SH146 can be reached by traveling west on FM2094, south on FM270, and east on SH96.

These closures are subject to change if needed due to weather.  