Traffic Shifts and Alternating Lane Closures on Bridge

On the Bridge:

  • Traffic shift on the existing SH146 bridge over Clear Creek Channel

    Concrete barriers will be placed on the bridge and the bridge will be re-striped to shift traffic to the west.  Two lanes will be maintained in each direction.  This traffic shift will create a work zone on the east edge of the bridge which will be used for widening (adding 1 new lane and 1 bicycle lane).

    • The barrier placement and striping will take place on the nights of 3/4/19 through 3/7/19, weather depending, from 9:00 pm - 5:00 am each night. During this time, there will be alternating lane closures on the bridge.

    • The barriers will remain in place until the northbound bridge widening is complete in approximately 15 months.

Connector Ramp to Shipyard

  • The connector ramp to Shipyard Drive (on the east side of the bridge) will be closed until completion of the northbound bridge widening.

Northbound SH 146

  • The outside lane on SH146 northbound from NASA Road 1 to Repsdorph Road will be closed during the day shifts of 3/4/19 through 3/7/19, from 9:00am to 3:00pm each day. This closure is to create a work zone for demolition/right-of-way clearing operations

South of the Bridge (Kemah)

  • The south U-turn/access road will be fully closed beginning on 3/4/19 at 9:00pm.  3rd Street, 4th Street, and 5th Street will no longer be accessible from this access road during this closure.  To reach 3rd Street, 4th Street, and 5th Street, traffic will turn east on 6th Street, then immediately turn north onto Texas Avenue.  This closure is necessary for the northbound bridge widening, for utility work, and to reconstruct the access road.  The closure will remain in place until the northbound bridge widening is complete in approximately 15 months